Case Study · State Street · July to October 2004

Project Manager · via ECL Management Consultants

The business case was a checklist that reached zero.

12Legacy systems decommissioned
€1MAnnual savings: realised, not modelled
4Months, end to end

Fig. 01 · Twelve systems retired, each verified first

Twelve systems off, each verified first.

Twelve systems retired, each verified as fully superseded first. System names withheld; recreated for this portfolio.

Client
State Street, global custodian and asset servicing provider
Role
Project Manager
Period
July to October 2004
Scope
Transfer of ABN AMRO Asset Management operations into State Street; multi-vendor coordination
Approach
Formal RAID discipline as the programme's shared single source of truth

The Brief

The hard part was that two estates had to become one (people, processes and systems from the transferring business landing inside the receiving organisation's operating model) with client service uninterrupted throughout, across multiple vendors, each with their own contract and their own interests. And the benefit was conditional: transfers routinely capture the migration and defer the decommissioning, leaving duplicate systems running 'temporarily' for years and the business case unrealised.

The Approach

The transfer ran on formal RAID discipline: risks, assumptions, issues and dependencies logged, owned and worked as the shared single source of truth across every vendor and internal team, because an issue without an owner is an issue that surfaces at cutover, and a dependency nobody tracks is a delay nobody expects. Decommissioning was managed as first-class delivery scope, not an afterthought: each of the twelve redundant systems was verified as fully superseded by the target estate before being switched off.

The delivery

Judgement Call

Prove supersession before switching anything off. Decommissioning a system in a live operations environment is irreversible in practice, so each retirement happened only once its functions were verified as fully covered. Caution about what to switch off, and evidence-backed confidence when switching it off, are the same judgement exercised decades later in deciding what to automate and what to leave manual.

What Was Delivered

  • The operations transfer completed with service continuity maintained throughout
  • Formal RAID-driven coordination across multiple vendors and internal teams: named deliverables, named owners, visible status
  • Twelve systems verified as superseded and decommissioned
  • €1M in recurring annual savings, delivered, not just modelled

The Outcome

The transfer completed in a four-month window with the consolidation benefit actually captured. The engagement's lasting contribution: a business case is only delivered when the old estate is switched off, and the transferable habit is managing the benefit as scope, with the same rigour as the migration itself.